Ram oil services company ltd. Undertakes to accomplish the whole requirements for the completion of wells job which includes the following services:

1- Workover rig operation.
2- Logging & perforation services.
3- Stimulation services.
a- wireline &fishing
b- Acidizing & coil tubing
c- Nitrogen pumping

the field works completion services for both producer wells(1-14) and.injecter wells(1-20) includes the following detailed operations: L. Rig up and remove x-mas tree and install bop
2. Pull-out existing strings and lay down
3. Pick-up new tubings and scrape casing to bottom of the well and circulate to clean
4 .pull-out of the hole
5. Run cbl,vdl,gr,ccl,(optional)**
6.run in hole 3lh" tubing and test with production packer to a depth 2300m average and set the packer at a depth 10m above tubings shoe and test
7. Remove bops and install x-mas tree and test
8. Move the rig to next location
9. Perforate the well 40m average interval with 2118 charges, 4 shot/ft
10. Displace the fluid in the well thruogh ssd and close ssd
11. Spot 5m3 15% hcl by coiled tubing i
12. Flow the well for the clenings (optional)
13. Acidize the well by 40m3 of 15% hcl with proper additives
14. Flow the well for cleanings (optional)
15. Squeeze the oil inside the well by treated water into the formation
16. Injectivity test to achieve break through by 3 regimes
17. Run floemeter while injection
18. Close the well for draw-down test (optional)
19. Temperature suivey after 72hrs of closing
20. Move equipment and hand-over the well



Jobs should be performed durings daylight
**bad cement intervals will not be treated