Electrical Projects - Mobile Substation at Al-Thaqir District, Basra City
Contract Title: Supply & Install New 132/11.5kV, 1X16MVA Mobile Substation at Al-Thaqir District, Basra City
Client:of Basrah / Basrah reconstruction unit
Contractor: ALDALHAM Co., IRAQ
Project Begin Date:17 Oct 2007
Project End Date:In progress




Scope of Works:
Supply of 132/11.5kV mobile substation including main transformer, auxiliary transformer, all switch gears & control panels to be mounted on flat bed trailer with construction of foundations & fencing to be connected to the existing network at Al-Thaqir District, Basra City